Installation Process
The essence of Next Century Building Sytems is the M2 Panel
M2 Panel Process
A modular panel with an expanded polystyrene core, enclosed in a double-galvanised steel wire mesh linked by connectors, to be finished on site with two layers of concrete. The M2 Panels cover the entire range of elements necessary to finalize any type of project in the building industry.
This quality facilitates the efficient management of the construction site, thus considerably saving time and money thanks to the quick and easy assembly of the components.
​
The M2 Panel System guarantees excellent earthquake resistance and thermal acoustic performances, and high-energy savings.

Step 1
Placing Rebars
The installation of M2 Panels starts by placing rebars of 8mm in diameter over the foundation beam, poured together with the concrete or drilled after, with a depth of 50mm using structural epoxy. Make sure to have the correct alignment of rebars with an interval of 400mm, alternating on both sides where the M2 panel will be placed.